# PERT / CPM "Crashing" the schedule

**Channel:** Professor Dansereau
**Source:** https://www.youtube.com/watch?v=zYnyGU9WSCk
**Transcript page:** https://www.withtranscript.ai/video/zYnyGU9WSCk

## Chapters

- 0:08 — Introduction to Crashing and Cost Columns
- 2:57 — Calculating Crash Periods and Costs
- 5:06 — Crashing the Critical Path Step by Step
- 8:09 — Reaching the Goal and Cost-Benefit Decision

## Transcript

**[0:08]:** Okay, today we're going to look at what's called crashing. Um, crashing is when we want to reduce the original schedule timewise, of course, at the lowest possible course cost. So, that reduction in time of the total schedule is called crashing or crashing the schedule. um we're still calling it per but technically once we start adding cost information in here this is where it becomes a CPM document. Um, so you notice I've added a couple of uh columns. Now, normal time. This is what we've been using as activity time

**[0:52]:** or, you know, if we looked at a standard uh curve, this would be the center of the time. Our crash time, this is telling us how many periods we have available to crash. So, we've gone through, we've done an analysis, we figured out that, you know, we could take two weeks out of the schedule um with our crash time. And the same thing with costs. Normal costs, this is how much it would cost us every day to run our operation. In crash costs, these are the extra costs we would incur. If you just assume, you know, to go from say with a from go to four weeks to two weeks, we've got to call in extra resources. Maybe we have to hire some part-time workers. Maybe we have to work overtime. Maybe we have to work Saturdays and Sundays. All that is going to add cost to our product um cost to our procedure, you know, because it's extra time, extra money.

**[1:48]:** Uh we're just condensing the schedule. Sometimes if we look at activity E here, you notice that we cannot crash the time. It's going to be 5 weeks either way. Think of it as like when you're baking a pie. You still have to cook the apple pie at 350° for about an hour. Um there's no real way to crash that. You can turn up the temperature, but all you do is burn the pie. So, it is what it is. You can't reduce this time. Um so, you notice the normal time and crash time don't change. and the normal cost and the crash cost don't change either. So once again normal means what we've been working with in the past. Um these are our activity times. We didn't look at costs before but these would have been our activity cost before. This is how much time we can reduce it to.

**[2:39]:** We can go from 9 weeks to 7 weeks for B here. Um, but our cost uh crash cost is going to be, you know, drive up our total cost by $100 in that case.

**[2:57]:** All right. Now, we're going to look at uh we have to add a little bit of more information so we can calculate. First thing we have to do is calculate how many crash periods we have available um or periods available to crash. how much we can reduce the schedule. That's simply normal time minus crash time. So our normal time is two or uh normal time is four. Our crash time is 2. So 4 - 2 you know equals 2. So we have two periods or in this case we're using weeks. So we have two weeks available to crash. Our next one we have 9 - 7. So we have 2 weeks available to crash there or two periods. U 9 - 8 is 1. Uh 3 - 2 is 1. Now we get to E where we didn't have any time available. So 5 - 5 is zero.

**[3:57]:** This indicates that we cannot uh crash D and we have one period available on F. So this gives us our crash periods available.

**[4:15]:** All right. Next, we're going to look at the cost to crash one period or the cost to crash per period if you will. It is simply our crash cost minus our normal cost. So, in this first one, my 1100 minus the 700 divided by our periods available to crash. We just calculated that. That's two. So 400 / two is 200 and I just followed suit all the way down. You notice when we get to E again um this would give us 0 over divided by zero and all you ASTU college students know that you can't divide by zero. It gets you an undefined number. So we can't do that one. It's another way of saying it's not available to crash.

**[5:06]:** Okay. Okay, now we're ready to crash. Um, from our diagram, I've plotted out the paths. We just happen to have six paths in this. I put in their associated times. Uh, we've identified the critical path. So, there's four steps we're going to do. First thing is we have to identify uh the critical path. Um then we start crashing the activity that had on the critical path that has the u uh lowest cost for one period. Um we adjust our our per CPM information and we repeat till we're done. Now let's just say your manager has given us you the goal of 16 weeks. You're currently at 18 weeks. To get to 16 weeks you get a huge bonus. So, it's in your best interest um to get it down to 16 weeks. Um I say that tongue and cheek, but a lot of times in contracts, you will have performance agreements that if you get a job completed earlier, your company will get a little bit more money and hopefully you'll as

**[6:12]:** the project manager, you'll get a slice of the pie there. All right, so this is our critical path. So, we start out by looking at what we can uh crash here. We have A which is 200. We have C which is 100 and E which is unavailable. All right. So obviously we want to take C. So we take C. Um so C goes from 9 to 8 and our critical path goes down to 17 weeks. We used up our one C though. We only had one period available to crash a C. So that goes from one to zero. All right. So we've crashed that one period and our C equals $100 so far. All right. Next, um you notice we effectively have two critical paths right now. We have two that equal 17. Um so it's uh uh we'll have to crash one then the second one.

**[7:20]:** So we'll have to do two steps here. One thing you sometimes look for if you have two critical paths, there's something common. So if you reduce it one unit, can you get, you know, the double the bang for your buck, so to speak? But unfortunately, our E here is unavailable to crash. So we can't do it on this one. All right, we just used up our C, so the only thing we can crash is A here. So we're going to crash A1 for $200. So I'm going to take my A. I'm going to reduce that down. I'm going to take my A here. Reduce this down. Technically that will also reduce the time of these paths here. Although they don't come into play in this problem.

**[8:09]:** Just to be technically correct, I'll go through and do that. Um, so but we still have we're still not at our 16week goal because we still have BDE here out of 17 weeks. So next we have to crash this. So we have our choice of B which is 50 um D which is 75 or E which is unavailable. So of course we're going to take the 50. Um this goes down to eight. This goes down to 16.

**[8:49]:** All right. But we also have the cost for B. Um, so you see now we're lucky enough to get down to 16 weeks everywhere with even though we have two critical paths, but we reached our goal of 16 weeks. So you're going to get that big bonus. Good job. at a cost of $350 because this is what it cost us to crash those three um items. Generally, what you would do is look at this. If you're going to get, you know, $500 performance bonus for getting it done in 6 weeks and it's only going to cost you $350, by all means, do it. Um but if this was more than your incentive, you there's other reasons not to do it.